Pittsburgh Regional Transit expects work on the Panhandle Bridge to affect light rail between Station Square and First Avenue beginning in spring 2027. The agency’s project page calls for trains to share one track through the work zone and anticipates periodic weekend closures with shuttle buses.

How would light rail service change?

Trains would take turns traveling across the Monongahela River between the two stations while crews work on the other track. PRT anticipates some bus and possible rail detours. Its project page gives a seasonal window for service impacts. Dated alerts will tell riders which trips change and where to board any replacement shuttle.

What is the construction timeline?

PRT’s project timeline lists preparation through December 2026, work on the outbound trackway during 2027, and work on the inbound trackway and overhead power system during 2028. PRT lists early 2029 for substantial completion and an anticipated construction value of $58 million. The construction phases and the dates riders see service changes are separate milestones.

Where should riders check before a trip?

Open PRT service alerts and look for your rail line, direction and travel date. For a trip that involves a transfer at Station Square or First Avenue, check the entire journey for changes. The Wire’s transit alerts guide explains where to find current notices.