Pittsburgh City Council voted Nov. 23 to approve a reimbursement agreement with PennDOT for preliminary design of the second phase of the Smithfield Street reconstruction. The vote covers the Downtown stretch between Forbes Avenue and Fort Pitt Boulevard. The Council meeting record lists the measure as passed.
What does the $900,000 cover?
The resolution caps preliminary design spending at $900,000. It lists $720,000 in federal highway funding and $180,000 in city bond funding, plus a separate city share of costs incurred by the state capped at $6,000. Construction would require its own funding and schedule.
Which blocks are already under construction?
The first phase broke ground in September and covers Forbes Avenue north to Sixth Avenue. Phase 2 runs south from Forbes to Fort Pitt Boulevard. The city’s Smithfield Street project page tracks the phases and posts project updates.
Where can I check current closures?
Use the Pittsburgh Downtown Partnership’s closure list for the work underway and Pittsburgh Regional Transit for bus detour information. A design vote sets no new closure dates for the southern blocks. Watch for design materials identifying changes to crossings, stops and access along that stretch.