Pittsburgh City Council held a November 25 hearing on a financing plan tied to two proposed East Liberty developments near Penn and Shady avenues. The plan projects about $10.1 million for public improvements and site work, including new traffic signals and crosswalk upgrades. As of November 28, the city’s legislative record still listed Bill 2026-1069 as held in Council, with no final action posted.

What the plan would fund

The October 30 implementation plan proposes about $3.12 million for sidewalks, open space, lighting and other public-space improvements, plus $2.12 million for signals, crossings and roadway work at Penn and Shady. Those two items account for just over half of the projected proceeds.

The rest would go toward brownfield cleanup, stormwater management, housing site preparation or infrastructure, and a $100,000 study involving Pittsburgh Regional Transit’s East Liberty garage and Larimer station. The study allocation does not establish a construction or service schedule. The exhibit estimates the broader package of infrastructure improvements at $23.7 million and identifies other possible funding sources.

The two sites behind the financing

The former Club One site is listed for 199 apartments and about 5,000 square feet of commercial or office space. The exhibit describes 5% of units as affordable within an 80% to 120% area median income range. It gives no application date or unit-by-unit rent schedule.

At the former Eastside Village Shopping Plaza, the plan anticipates 150,000 to 175,000 square feet of mixed-use development that could include housing, retail, hospitality and offices. The exhibit estimates the combined development cost at about $180.6 million.

Where the money would come from

The proposal would direct 70% of the projected increase in real estate tax revenue from the pledged development to district financing or project costs. The city, Allegheny County and Pittsburgh Public Schools would split the other 30% of the increase proportionally. The proposed 20-year period would begin for each pledged project once it is completed and reassessed. That ties the timing and amount of the proceeds to what gets built and how the properties are valued.

The plan lists nine parcels across the two sites with a combined taxable assessed value of about $16.6 million. Its forecast assumes that assessed value rises to $85 million after development. Using 2026 tax rates, the exhibit puts annual real estate tax revenue at about $440,000 today and $2.26 million after full development. Of the projected $1.82 million annual increase, roughly $1.27 million would go toward district financing or project costs under the proposed split. The rest of the increase would flow to the three taxing bodies. Those calculations depend on buildout and future assessments.

What to watch after the hearing

The next sign of progress is a recorded Council action on Bill 2026-1069. Readers following a specific crossing, sidewalk or housing proposal should also look for later project-level budgets, approvals and schedules. The November 25 hearing record lists its minutes as draft.

Council’s Standing Committees amended the bill on November 10 before sending it to a public hearing. The financing figures above come from the version 2 exhibit attached to the bill.